Water Distribution
-
Be able to experimental run simulation without commit in WS Pro
Be able to experimental runs simulation without commit in WS Pro
10 votes -
Import demand scaling using CSV file on WS PRO
Please add the ability to import demand scaling using CSV file on WS PRO
8 votes -
Can you include scenarios in WS pro environment similar to ICM
ICM got the capability of the scenario modelling within the single network. H2Omap also had the same capability. Any possibility of having the same capability in WS pro?
30 votes -
As a user it is good to allow tab windows to take it out to the second or third display
Tab windows are not allowed to move main window to second display.
2 votes -
Allow InfoWater to export simulation results in CSV format instead of DBF
The option to "Export simulation results for external application" in InfoWater would be more useful if the results were exported as CSV files instead of DBF files. We regularly need to compare the results from multiple model scenarios. Microsoft PowerBI or Excel PowerQuery are great tools for importing and comparing large amounts of data and could streamline this process significantly. However, neither support importing directly from DBF files.
1 vote -
Make InfoWater windows and dialog boxes resizable
Many windows in InfoWater/InfoWater Pro are not resizable, making it difficult to see long values.
1 vote -
Add zoom to and map navigation ability in the report tables for InfoWater Pro
I use both Bentley and Innovyze water modeling software and i have noticed that the Bentley software allows you to zoom to elements from the report tables and allows you to pan, click, review properties, etc. while the report table is open. It would be really nice if Innovyze could include a zoom to feature in the report tables (similar to what is already included in the DB editor), and allow the user to pan around in the map and click on elements while the report table is open.
2 votes -
InfoWater: Report volume stored in tanks
I can calculate volume from level, but it's an extra step and requires that I copy the run results out to Excel. It's even more difficult if I have a non-circular tank. Please include tank volume in the tank results and in the "System Demand" report.
1 vote -
Allow Ctrl+C and Ctrl+V in InfoWater Pro
I could always copy and paste attributes via simple keyboard commands (Ctrl+C and Ctrl+V) in classic InfoWater, but can no longer do that in InfoWater Pro. You can right click and select "Copy" or "Paste", but that takes longer. Bring back keyboard commands.
8 votes -
Multi-thread simulations
As a user I want to take advantage of multi-threaded CPUs to accelerate simulation intensive procedures (e.g. design calibration)
22 votes -
Sort selection sets/ re-order them
Would be very useful if you could either sort selection set orders or move selections up or down the list. This would make it much faster to find the selection set you want in a large list (e.g. DMA selection sets in alphabetical order)
1 vote -
I would like more informative error messages when trying to Change an ID
I tried to change the ID for a pump, but I overlooked the “Target Element Type” dropdown, which was automatically set to junction.
It took me a while to realize my mistake. It might be helpful to other users if the error messages/warnings (see below) were a bit more informative… I’d suggest something like “WARNING: Junction ID ‘P1240’ does not exist.” I think this would have helped me realize my error much sooner.
WARNING: unable to change Junction ID from 'P1240' to 'P1241'.
MESSAGE: no Junction ID was changed.2 votes -
InfoWater for QGIS
ArcMap and ArcGIS Pro are expensive and slow. QGIS is free and fast.
2 votes -
Node Name Generation Default
In WS PRO it would be great to be able to set Node Name Generation format as a default for all networks in a database instead of having to enter it in every time I want to add nodes to a network
5 votes -
Combine simple and rule-based controls dialogs
It is currently difficult to identify if a facility has a rule-based control. An improvement would be to access all the controls for a facility through the existing controls button. Clicking the controls button would open a single window with a tab for simple controls and a tab for logical controls.
6 votes -
Edit Pump and Valve Curves in IWLive
IWLive is the perfect platform to examine how well valve and pump curves are simulating the actual behavior under a wide range of system conditions. If these could be modified in an incident run, it would save lots of time going back to WS to modify them.
2 votes -
Be able to change the background colour
In InfoWorks the background colour for the GeoPlan is white - it would be beneficial to change this colour to the users choice to make particular features stand-out more clearly in the GeoPlan view
3 votes -
Add new run groups and move existing runs to these
I’ve currently got one very big run group which should’ve really been split into several different ones.
Is there a way to move around runs? In the explorer there’s only really the option to duplicate.3 votes -
Boundary trace toolbar shortcut
I often use the boundary trace tool to understand the extent of a DMA/PMA. Currently, we have to go to Geoplan -> Tracing Tools -> Boundary Trace, and it would be a lot easier if it was available as a toolbar shortcut.
3 votes -
Add ability to rename datasets, patterns, queries, etc
- Allow the "Change ID" tool to rename datasets, patterns, queries, etc.
- Make the "Change ID" window wider or resizeable to fit longer IDs.
6 votes
- Don't see your idea?